This project consists of replacing, upsizing, and realigning approximately 5,000 lineal feet of existing 24-inch, 27-inch, and 39-inch diameter trunk sewer main via open trench construction with 30-inch and 36-inch diameter trunk sewer main; construct approximately 200 lineal feet of 48-inch diameter casing with 36-inch diameter sewer carrier pipe via trenchless construction; construct approximately 1,200 lineal feet of 8-inch diameter sewer main; and construct approximately 100 lineal feet of 24-inch diameter sewer main.  This project is located between the Hale Avenue Resource Recovery Facility and the intersection of Quince Street and Norlak Avenue.
 

Estimated Construction Schedule – 440 calendar days; The City Council awarded the project to Southland Paving, Inc. on February 8, 2023, in the amount of $8,482,904.64.  Notice to proceed was issued on August 15, 2023.  Construction is scheduled to begin September 2023.

Contact:
Randy Manns – Utilities Construction Project Manager 760-839-6290, ext. 7031
Eric Iglesias – Field Engineering Inspector 760-504-9373