This project consists of the replacement of approximately 5,500 lineal feet of existing 10-inch and 12-inch cast iron water pipeline with 12-inch PVC pipeline; and replacement of existing water services, water meters and a fire hydrant.  The project is located along West 7th Avenue from Quince Street to South Broadway, and in South Broadway from West 7th Avenue to West Valley Parkway. 

Estimated Construction Schedule – 220 calendar days; The City Council awarded the project to S.C. Valley Engineering, Inc. on Dec 1, 2021, in the amount of $2,985,960.  Notice to proceed was issued on Jan 18, 2022.  Construction began in January 2022 and expected to be completed by September 2022.

Contacts:

Eric Iglesias – Field Engineering Inspector 760-504-9373

Sam Lopez – Field Engineering Inspector 442-777-8842

Randy Manns – Utilities Construction Project Manager 760-839-6290 x7031