FOR IMMEDIATE RELEASE

Contact: Joyce Masterson, 760-839-4621

Over the next several weeks construction on the Maple Street Pedestrian Plaza will take place at night in order to minimize daytime traffic congestion on Valley Parkway between Broadway and Escondido Boulevard.  As a result the following lane closures will occur:

  • Starting Sunday night, 4.22.12 through 4.27.12, from 7:00 p.m. to 5:00 a.m., west bound Valley Parkway from Broadway to Maple will have two lanes on the north side of the street closed.  One lane on the south side will remain open. 
  • The following Monday, 4.30.12 to 5.4.12, from 7:00 p.m. to 5:00 a.m., west bound Valley from Broadway to Maple will have two lanes on the south side closed and one lane on the north side will remain open.

 In order to accommodate Crusin’ Grand, work on Friday nights will not start until 9:00 p.m.

 ###