If you have any questions concerning the schedule or any related engineering questions, please contact the Engineering Division at (760) 839-4651 and identify the project as an Individual Building Site, a Parcel Map, or a Subdivision, so that you are referred to the correct section.
| Individual Building Site |
Time to Complete |
| Applicant requests building permit. |
|
| Building Department notifies Engineering. |
1-2 days |
| Engineering reviews site. |
|
| Engineering writes conditions for development. |
|
| Conditions forwarded to applicant via Building Department. |
Varies |
| Applicant contacts Engineering to be informed on how to complete conditions. |
Varies (unknown) |
| Applicant submits plans to Engineering. |
Varies (unknown) |
| Engineering processes and checks plans. |
Varies (2-3 checks) |
| Conditions satisfied. Security posted. Plans signed. |
Varies |
| Engineering releases building permit. |
|
| Plans transmitted to Field Office for inspection. |
Same day |
| Field Inspector inspects construction site (various times). |
When notified |
| Applicant requests final inspection and correction list. |
Varies |
| Field Engineer releases utilities upon completion. |
Upon completion |
| Field Engineer releases securities post by applicant. |
Within 2 weeks |
| Applicant/Owner moves into home/building. |
|
| Parcel Map (4 lots or less) |
Time to Complete |
| Applicant meets with Engineering to discuss proposed division of parcel. |
|
| Applicant submits Tentative Map to Planning for E.I.R. review. |
|
| Planning distributes Tentative Map to Engineering for review. |
Within 1 week |
| Engineering reviews Tentative Map and makes comments which are forwarded to Planning. |
Varies (workload) |
| Planning notifies applicant of comments and declares Negative Declaration. |
Varies |
| Applicant submits Tentative Map to Planning for Conditions of Approval. |
Varies (unknown) |
| Planning distributes Tentative Map to Engineering and other departments. |
Within 2 days |
| Engineering writes Conditions of Approval. Engineering collects other department's conditions and consolidates. |
Varies (within 50 days) |
| Applicant is notified in writing of conditions necessary to complete Parcel Map. |
Varies (within 50 days) |
| Applicant is given an appeal period on any of the conditions. |
10 days |
| Applicant contacts Engineering to begin completion of conditions. |
Varies (unknown) |
| Applicant's engineer submits Final Map and plans for processing by Engineering. |
Varies (unknown) |
| Conditions satisfied. Security posted. Map approved. Plans signed. |
Varies (within 1 year) |
| Map recorded. Applicant may sell parcels. |
Varies |
| Plans transmitted to Field Office for inspection. |
Immediately |
| Field Inspector inspects construction site (various times). |
When notified |
| Applicant requests final inspection and correction list. |
Varies |
| Field Engineer releases utilities upon completion and acceptance of entire project. |
Upon completion |
| Field Engineer releases securities posted by applicant. |
Within 2 weeks |
| Subdivision (5 or more lots) |
Time to Complete |
| Concept meetings with developer and Planning. |
Varies |
| Developer submits Tentative Map to Planning for E.I.R. review. |
Varies (unknown) |
| Planning distributes Tentative Map to Engineering for comments. |
Within 1 week |
| Engineering reviews Tentative Map. E.I.R. comments are forwarded to Planning. |
Varies (workload) |
| Planning notifies developer of Negative Declaration or full draft. |
Varies (A.S.A.P.) |
| Developer files Tentative Map with Planning. |
Varies (unknown) |
| Planning distributes Tentative Map to Engineering and other departments. |
Within 2 days |
| Engineering writes Conditions of Approval and submits to Planning. |
Varies (2 weeks) |
| Planning presents Tentative Map to Planning Commission . |
Within 50 days |
| Planning Commission approves or rejects Tentative Map. |
At meeting |
| Planning presents Tentative Map to City Council for approval. |
Within 81 days |
| Upon approval by City Council, developer prepares final map and improvement plans. |
Varies (unknown) |
| Developer's engineer submits Final Map and plans for processing and checking by Engineering (several checks). |
Varies (depends on plans) |
| Conditions satisfied. Security posted. Agreements signed. Final Map recommendation to City Council. |
Varies |
| Map signed by City Engineer and forwarded to County Clerk for recording. |
Upon Council approval |
| Developer may sell parcels. |
Upon recordation |
| Plans transmitted to Field Office for inspection. |
Varies |
| Field Inspector inspects construction site (many times). |
When notified |
| Developer requests final inspection and correction list. |
Varies |
| Field Engineer releases utilities upon completion and acceptance of improvements. |
Upon completion |
| Field Engineer releases securities posted by developer. |
Upon final acceptance |