Building Site Processing


We have prepared schedules showing how a building site is processed through the City of Escondido, particularly the Engineering Division. Hopefully, this will assist you in better understanding the processing of your project.

If you have any questions concerning the schedule or any related engineering questions, please contact the Engineering Division at (760) 839-4651 and identify the project as an Individual Building Site, a Parcel Map, or a Subdivision, so that you are referred to the correct section.

Policy Statement for Plan Checking

Individual Building Site Time to Complete
Applicant requests building permit.   
Building Department notifies Engineering. 1-2 days
Engineering reviews site.  
Engineering writes conditions for development.  
Conditions forwarded to applicant via Building Department. Varies
Applicant contacts Engineering to be informed on how to complete conditions. Varies (unknown)
Applicant submits plans to Engineering. Varies (unknown)
Engineering processes and checks plans. Varies (2-3 checks)
Conditions satisfied. Security posted. Plans signed. Varies
Engineering releases building permit.  
Plans transmitted to Field Office for inspection. Same day
Field Inspector inspects construction site (various times). When notified
Applicant requests final inspection and correction list. Varies
Field Engineer releases utilities upon completion. Upon completion
Field Engineer releases securities post by applicant. Within 2 weeks
Applicant/Owner moves into home/building.  



Parcel Map (4 lots or less) Time to Complete
Applicant meets with Engineering to discuss proposed division of parcel.  
Applicant submits Tentative Map to Planning for E.I.R. review.  
Planning distributes Tentative Map to Engineering for review. Within 1 week
Engineering reviews Tentative Map and makes comments which are forwarded to Planning. Varies (workload)
Planning notifies applicant of comments and declares Negative Declaration. Varies
Applicant submits Tentative Map to Planning for Conditions of Approval. Varies (unknown)
Planning distributes Tentative Map to Engineering and other departments. Within 2 days
Engineering writes Conditions of Approval. Engineering collects other department's conditions and consolidates. Varies (within 50 days)
Applicant is notified in writing of conditions necessary to complete Parcel Map. Varies (within 50 days)
Applicant is given an appeal period on any of the conditions. 10 days
Applicant contacts Engineering to begin completion of conditions. Varies (unknown)
Applicant's engineer submits Final Map and plans for processing by Engineering. Varies (unknown)
Conditions satisfied. Security posted. Map approved. Plans signed. Varies (within 1 year)
Map recorded. Applicant may sell parcels. Varies
Plans transmitted to Field Office for inspection. Immediately
Field Inspector inspects construction site (various times). When notified
Applicant requests final inspection and correction list. Varies
Field Engineer releases utilities upon completion and acceptance of entire project. Upon completion
Field Engineer releases securities posted by applicant. Within 2 weeks



Subdivision (5 or more lots) Time to Complete
Concept meetings with developer and Planning. Varies
Developer submits Tentative Map to Planning for E.I.R. review. Varies (unknown)
Planning distributes Tentative Map to Engineering for comments. Within 1 week
Engineering reviews Tentative Map. E.I.R. comments are forwarded to Planning. Varies (workload)
Planning notifies developer of Negative Declaration or full draft.  Varies (A.S.A.P.)
Developer files Tentative Map with Planning. Varies (unknown)
Planning distributes Tentative Map to Engineering and other departments. Within 2 days
Engineering writes Conditions of Approval and submits to Planning. Varies (2 weeks)
Planning presents Tentative Map to Planning Commission . Within 50 days
Planning Commission approves or rejects Tentative Map. At meeting
Planning presents Tentative Map to City Council for approval. Within 81 days
Upon approval by City Council, developer prepares final map and improvement plans. Varies (unknown)
Developer's engineer submits Final Map and plans for processing and checking by Engineering (several checks). Varies (depends on plans)
Conditions satisfied. Security posted. Agreements signed. Final Map recommendation to City Council. Varies
Map signed by City Engineer and forwarded to County Clerk for recording. Upon Council approval
Developer may sell parcels. Upon recordation
Plans transmitted to Field Office for inspection. Varies
Field Inspector inspects construction site (many times). When notified
Developer requests final inspection and correction list. Varies
Field Engineer releases utilities upon completion and acceptance of improvements. Upon completion
Field Engineer releases securities posted by developer. Upon final acceptance


WelcomeEscondido At A GlanceCity Council & Commissions
City DepartmentsCity EmploymentEconomic Development
What's New(s)Arts, Entertainment & EventsGovernment Links
E-ServicesEscondido A-ZSearchMain Page